Summary

Enables an underground‑specific Bulk Action: “Mark Hole as Checked”.  This enhancement improves Prep Crew efficiency and productivity by allowing users to quickly mark multiple holes as meeting site prepping standards, reducing the number of interactions required with the BlastIQ™ Mobile device.

 

How to Use

  1. Open a blast and tap the "Bulk Action" button in the toolbar. 

    • Note:  This feature is only available during the Prepping phase.
    HowToUse1.png
  2. On the "Bulk Edit" screen, tap "Checked" to mark the hole as checked.

    HowToUse2.png
  3. To clear a status, tap "Clear checked".
  4. Tap the Apply button to proceed.

    HowToUse3-4.png
  5. Once applied, the hole status will be updated immediately.

 

Qualification Rules for "Mark Hole as Checked"

For a hole to qualify for Mark Hole as Checked, all of the following conditions must be met:

  • No actual measurements have been recorded for:
    • Length and  Diameter 
  • The hole is not already marked as checked.
  • The hole is not any of the following states:
    • not_drilled, dipped, stemmed, partially loaded, explosives loaded, abandoned, and conflicting measurements.

 

Note:  

For configuration details, refer to the article How to enable checked holes in Underground